Tianjin SMIC Tianxiang Project Phase II FMCS Engineering Power System and Cleanroom System Installation Project

Construction time: September 1, 2020 - January 30, 2021

Building area: 230,000㎡

Clean area: 74,000㎡

Cleanliness level: Class 100

Scope of contracting: Tianxiang Phase II cleanroom and electromechanical engineering

Project highlights: this project is about the space management, manufacturing, procurement and supply, transportation (including secondary lightering), unstuffing and unloading, insurance, warehousing, placement, installation and commissioning, trial operation, cooperative acceptance, training, after-sales service, spare parts, special tools, defects liability period, quality guarantee period, and other related services of the corresponding cleanrooms and general electromechanical systems.

 