Construction time: February 5, 2018 - May 31, 2018
Building area: 44,400㎡
Clean area: 18,000㎡
Cleanroom level: Class 10,000 - 1,000,000
Product features: R&D and production of highly digital and intelligent lithium batteries
Scope of contracting: plant cleanrooms
1.The E-Power Project focused on the R&D of power batteries for medium and high-end passenger vehicles to provide advanced power battery solutions for green transportation. Based on the core technology of ternary li-ion power batteries with high safety, long cycle and high specific energy, a highly digital and intelligent battery R&D and production base was built.
2.The entire lithium battery R&D and production system, including PTO preparation line and the production line of power batteries and modules, and the civil construction of the power station. It took only 10 months from the commencement to the moving in of the equipment, breaking the fastest plant building speed again in the new energy lithium battery industry.