Construction time: November 5, 2017 - December 31, 2017
Building area: 43,500㎡
Clean area: 38,000㎡
Cleanliness level: Class 100,000
Scope of contracting: plant electromechanical engineering, FMSC
Project highlights:the annual production capacity of Shanxi Jinneng Project is 300mW thin-film solar modules, and it adopts the latest process of national new energy solar energy.
Aerial view
Live view of the project
Project awards
Advanced Unit