Construction time: July 30, 2020 - November 27, 2020 (contract construction period for section 1, and that of section 2 is subject to the notice of the owner)
Building area: 55,000㎡
Clean area: 13,000㎡
Cleanliness level: Class 100,000
Scope of contracting: Sinoma Lithium Battery Separator Buildings 3#, 4#, 5#, and 6#, and power station, steam pressure regulating station, outdoor pipe gallery, and plant electrical engineering
Project highlights:this project is about the purification system engineering, public works (deepening design scheme, construction organization design and maintenance services, space management, etc.), and materials and equipment supply and installation, decoration, HVAC, electrical engineering and piping, and subsystem installation, system commissioning, acceptance, training, and after-sales service, and the supply of all equipment and materials (except for those supplied by Party A) required for the completion and acceptance of the project and the acceptance of other professional departments, and related work. This project will serve as a benchmark project for the company's undertaking of projects in the lithium battery separator industry and talent training base.
Industry value:As a leading new energy manufacturing service enterprise in China, Sinoma Lithium Battery Separator Group is a company under the CBMI Construction Co., Ltd., one of the Fortune Global 500 companies, and its main products are 5-20μm wet process two-way synchronous stretching separators and various types of coated separators, which are used in new energy vehicle power batteries, 3C consumer batteries, energy storage batteries and other fields, providing a strong guarantee for the vigorous development of China's battery industry.
Figure 1 Aerial view of the project
Figure 2 Aerial view of the power station