COVID-19 Vaccine Workshop Project of the Institute of Medical Biology, Chinese Academy of Medical Sciences

Construction time: May 6, 2020 to September15, 2020

Building area: About 4,605㎡

Clean area: 2,795㎡

Cleanliness level: Maximum Class A

Scope of contracting:The construction scope includes all electromechanical installation engineering such as purification and decoration of F/3 of Building #3, HVAC, utility works, process water and gas distribution system, water supply & drainage, electricity, fire control, etc., as well as the mounting/installation of relevant equipment.

Project highlights:The systems for this project include: Cleanroom environment system, cleanroom air supply and exhaust processing system, process cooling water system, electrical system, FMCS system, water supply and drainage system, automatic fire alarm system, main pipeline system, etc. The project is positioned as a biosafety P3 vaccine workshop project, which sets higher standards for air tightness of the maintenance structure and for the construction technology of sockets and process power distribution system in the room; The rooms are densely distributed, and the requirements for pressure difference gradient in the rooms are high (no reversal in state switching) and it is difficult to carry out commissioning. The commissioning/verification/acceptance of each system shall be completed according to GMP specifications etc.

Industry value:Boost Institute of Medical Biology, Chinese Academy of Medical Sciences to fight against Covid-19 epidemic, build GMP production workshop with biosafety protection function, and make contributions to safeguarding people's life and health, safeguarding national public health safety and jointly coping with the novel Covid-19 epidemic worldwide.

 