Construction unit: Chongqing HKC Jinyu Optoelectronics Technology Co. Ltd.
Project location: Banan Economic Park, Chongqing City
Service content: project management, scheme design, preliminary design, construction drawing design
Project investment: RMB 12 billion
Construction scale: total occupied area: 600 mu; total building area of Phase I: 350,000㎡; cleanroom area of Phase I: 220,000㎡
Construction period: December 2015 - July 2017
Project product: G8.5+ TFT-LCD
Project capacity: 75K pieces/month