Anhui Huasheng Photovoltaic Industry Standardized Factory Mechanical and Electrical Installation EPC Project

Construction period: December 5th, 2021 to May 20th, 2022

Building area: 85000 square meters

Clean area: 23000 square meters

Cleanliness level: up to Class 1000

Scope of Contracting: EPC project, including clean electromechanical package in the main factory building of Huasheng New Energy's 2GW battery, power station and warehouse electromechanical engineering, wastewater treatment station CDS1、 Class A Warehouse 1, Class A Warehouse 2, Silane Station, Hydrogen Station, Solid Waste Station, Bulk Gas Station, Wastewater Lifting Station Civil Engineering+Light Steel Structure+Mechanical and Electrical Engineering+Partial Auxiliary Engineering, Partial Office Fine Decoration Project.

Category:
 
 

Project Highlights: This project includes the design, procurement and supply, engineering construction, transportation (including secondary transportation), unpacking and unloading, insurance, warehousing, positioning, installation and commissioning, trial operation, cooperation and acceptance, training, after-sales service, spare parts, special tools, defect liability period, quality assurance period, and other related services for the corresponding clean room and supporting individual civil engineering and general electromechanical systems. The system includes but is not limited to: clean room environmental system, clean room fresh air treatment system, non clean area air conditioning system, process exhaust system, process cooling water system, pure water system, wastewater treatment system, special and bulk gas system, chemical supply system, electrical system, FMCS system, water supply and drainage system, smoke control and emergency exhaust system, supporting functional unit civil engineering and light steel structure engineering and decoration engineering, process equipment department and factory office decoration engineering, etc.

Industry value: This 2GW battery production line is the industry's first large-scale, high-capacity microcrystalline process production line at the GW level. The average efficiency of battery production can reach over 25%, making it the most efficient intelligent workshop in the industry.






Aerial view

Construction of cleanroom interior

Project groundbreaking ceremony: Shi Zhengming, General Consultant of Huasheng New Energy, and Chairman Li Nan took a group photo to commemorate the occasion

Project groundbreaking ceremony: Our Chairman Li Nan and other leaders took a group photo with the project team to commemorate the occasion

Process equipment moving in ceremony: Liu Jiahe, Director of Xuancheng Economic Development Zone Management Committee, Xu Xiaohua, Chairman of Huasheng New Energy, and Yang Liangsheng, General Manager of our company, attended the equipment moving in ceremony

General Manager Yang Liangsheng and other leaders of the company took a group photo with the project management team to commemorate the occasion

 