Annual production of 1.5GW high-efficiency solar cell module intelligent manufacturing project

Construction period: January 2022 to October 2022

Building area: 51260 square meters

Contracting mode: Construction general contracting

Service content: Civil engineering, HVAC, decoration and renovation, intelligent (air conditioning self-control), etc

Product: Solar Photovoltaic Panel

Category:
 
 

Industry value: China Energy Conservation and Environmental Protection Corporation (CECEP) is a holding subsidiary of China Energy Conservation and Environmental Protection Corporation (CECEP). China Energy Conservation and Environmental Protection Group Corporation is a central enterprise mainly engaged in energy conservation, emission reduction, and environmental protection. China Energy Saving Solar Energy Co., Ltd. is one of the largest solar power plant investment and operation companies in China, and the first listed company in China to focus on solar power generation, with total assets of 30 billion yuan.

Milestone significance: The cooperation between China Electric Power Second Company and China Energy Conservation Solar Energy Technology (Zhenjiang) Co., Ltd. has been elevated, and the original cooperation content has been expanded, which is of great significance for China Electric Power Second Company's transformation from mechanical and electrical general contracting to construction general contracting and EPC construction.

Project highlights: By leveraging experience, planning in advance, fully prefabricating, and shortening the construction period (actively responding, taking responsibility, and fully prefabricating)
1. During the bidding process, project planning should be done well, and after the bid is awarded, personnel should immediately enter the site
2. During civil engineering, the mechanical and electrical construction part was already taken into consideration. After entering the site, according to the overall packaging requirements of the owner, a plan was made and a lot of promotion work was done in cooperation with the owner
3. Before the secondary assembly, actively confirm the parameters and use past construction experience to determine the material scheme in advance, including the prefabrication and prefabrication of supports, hangers, and valve groups.

 

 
 